[Please enable JavaScript.] [Please enable JavaScript.] 421 S 21st StMattoon, IL 61938

8-5 M-F

What We've Been Up to Lately

Main Level of Charleston remodel ENters Home Stretch!

Jan 14

We have entered the final phases of the main floor remodel in Charleston.  Currently all cabinetry is in place, all new floors, all trim, doors and casing are installed. We are expecting countertops Wednesday morning, before entering the final stages of the plumbing and electrical system. We will now also start the finishes of the hall bath and laundry room. We will complete as much of the hall bath as we can before we start final stairwell finishes and final paint.  As a whole everything is going smoothly, great customers make everything easier. Our trade partners continue to excel at all times.... Onward we go....IMG_30851.jpgIMG_30881.jpgIMG_30891.jpg